Implementation of lean practices facilitated by BIM functionalities in the construction phase: advances and opportunities

Renato Nunes Mariz e Flavio Augusto Picchi

em inglês

cita 104 obras

resumo

Abstract Over the past few decades, construction productivity has been at a standstill. Lean and Building Information Modelling (BIM) is attracting increasing interest in the construction industry as a way to increase construction productivity. This paper aims to contribute to the body of knowledge by identifying hitherto unexplored opportunities for the use of BIM functionalities as a support and as facilitators of the application of lean practices in the construction phase. A systematic literature review was adopted as the methodological approach in this research, and reported case studies related to the scope of this paper were searched. The results show that lean practices can be classified into four degrees of BIM support based on the level of current exploration. Just one lean practice (the last planner system) has been extensively explored, three have been reasonably explored, and five have just been preliminarily explored. Five practices have not been explored at all. This research summarises the already studied and the potential additional uses of BIM functionalities to support each lean practice, showing that lean practices supported by BIM functionalities are still underused and that further studies can explore additional ways to support these practices. This study holds great value for a broader practical application of lean practices, bringing faster and easier results with more extensive BIM support.

como citar · ABNT NBR 6023

MARIZ, Renato Nunes; PICCHI, Flavio Augusto. Implementation of lean practices facilitated by BIM functionalities in the construction phase: advances and opportunities. Ambiente Construído, 2021. DOI: 10.1590/S1678-86212021000400571.

Referências

104 obras citadas

  1. 1J. S. ÁLVARES e D. B. COSTA. Construction progress monitoring using unmanned aerial system and 4D BIM. 2019quem mais cita →
  2. 2T. D. C. ALVES. Incentives and innovation to sustain lean construction implementation. 2009quem mais cita →
  3. 3R. ARBULU, G. BALLARD e N. HARPER. Kanban in construction. 2003quem mais cita →
  4. 4D. ARDITI, O. B. TOKDEMIR e K. SUH. Challenges in line-of-balance scheduling. Journal of Construction, Engineering and Management, 2002quem mais cita →
  5. 5T. BAINES. State-of-the-art in lean design engineering: a literature review on white-collar lean. Journal of Engineering Manufacture, 2006quem mais cita →
  6. 6G. BALLARD e G. A. HOWELL. An Update on Last Planner. 2003quem mais cita →
  7. 7G. BALLARD e I. TOMMELEIN. Current process benchmark for the Last Planner System. Lean Construction Journal, 2016quem mais cita →
  8. 8G. BARBOSA. Heijunka system to level telescopic forklift activities using tablets in construction site. 2013quem mais cita →
  9. 9F. S. BATAGLIN. Model for planning and controlling the delivery and assembly of engineer-to-order prefabricated building systems: exploring synergies between Lean and BIM. Canadian Journal of Civil Engineering, 2019quem mais cita →
  10. 10L. BEN-ALON e R. SACKS. Simulating and visualizing emergent production in construction (epic) using agents and BIM. 2015quem mais cita →
  11. 11A. BHATLA e F. LEITE. Integration framework pf BIM with the Last Planner System. 2012quem mais cita →
  12. 12M. BINNINGER. How can lean construction improve the daily schedule of a construction manager. 2017quem mais cita →
  13. 13C. BIOTTO. Adapted use of andon in a horizontal residential construction project. 2014quem mais cita →
  14. 14A. BJÖRNFOT e R. JONGELING. Application of line of balance and 4D CAD for lean planning. Construction Inovation, 2007quem mais cita →
  15. 15R. BORTOLINI, C. T. FORMOSO e D. D. VIANA. Site logistics planning and control for engineer-to-order prefabricated building systems using BIM 4D modeling. Automation in Construction, 2019quem mais cita →
  16. 16R. BORTOLINI, J. S. SHIGAKI e C. T. FORMOSO. Site logistic planning and control using 4D modeling: a study in a lean car factory building site. 2015quem mais cita →
  17. 17P. BRERETON. Lessons from applying the systematic literature review process within the software engineering domain. Journal of Systems and Software, 2007quem mais cita →
  18. 18I. R. BULHÕES, F. A. PICCHI e A. D. GRANJA. Combining value stream and process levels analysis for continuous flow implementation in construction. 2005quem mais cita →
  19. 19A. Q. CARNEIRO. Development and evolution of project production systems: the PS-37. 2009quem mais cita →
  20. 20J. C. P. CHENG, Q. LU e Y. DENG. Analytical review and evaluation of civil information modeling. Automation in Construction, 2016quem mais cita →
1–20 de 104 obras citadas

Quem cita esta obra

nenhum artigo do acervo cita esta obra — ainda

É sua obra?

Receba um aviso quando um artigo novo citar este trabalho.

também serve para acompanhar o autor que você estuda
Acompanhar as citações