Construction duration predictive model based on factorial analysis and fuzzy logic
Luiz Maurício Furtado Maués, José Alberto Silva de Sá, Carlos Tavares da Costa Junior, Andrea Parise Kern e André Augusto Azevedo Montenegro Duarte
em inglês
citado por 1 artigocita 59 obras, 3 no acervo
resumo
Abstract Setting the building construction duration for vertical residential works is made still in the study phase of economic and financial feasibility of the project and, in most cases, in an empirical way, increasing the uncertainties and the risks to fulfill the set deadline. However, there are computational intelligence tools that can contribute to reduce the degree of uncertainty. This study aimed to investigate the use of a hybrid system to estimate the deadline for vertical residential building works from design and production characteristics using factorial analysis and Fuzzy Systems. To this end, we used information of a database from the SEURB and in some buildings construction companies in Belém, a city located in the State of Pará, northern of Brazil. For the training and construction of the Fuzzy Forecast Model, data from 71 projects were used and 16 others residential buildings were used for its validation. The results showed a significant level of assertiveness, with 75% accuracy considering a range, whose upper and lower limits were calculated from MAPE and MASE. The model presented a prediction performance superior to other models already consecrated in the literature.
como citar · ABNT NBR 6023
MAUÉS, Luiz Maurício Furtado et al. Construction duration predictive model based on factorial analysis and fuzzy logic. Ambiente Construído, 2019. DOI: 10.1590/S1678-86212019000400346.
Referências
59 obras citadas · 3 no acervo
- 1M. AHMADI. Comprehensive Risk Management Using Fuzzy FMEA and MCDA Techniques in Highway Construction Projects. Journal of Civil Engineering and Management, 2017quem mais cita →
- 2H. A. AHMADU. Modelling Building Construction Durations. Journal of Financial Management of Property and Construction, 2015quem mais cita →
- 3K. AHSAN e I. GUNAWAN. Analysis of Cost and Schedule Performance of International Development Projects. International Journal of Project Management, 2010quem mais cita →
- 4A. T. de ALMEIDA. Processo de Decisão nas Organizações: construindo modelos de decisão multicritério. 2013quem mais cita →
- 5F. BROMILOW. Contract Time Performance Expectations and the Reality. Proceedings..., 1969quem mais cita →
- 6D. C. BUZZI. Diretrizes Para o Gerenciamento de Riscos em Incorporadoras da Construção Civil: uma abordagem utilizando lógica difusa. 2010quem mais cita →
- 7I. C. CÁRDENAS. Modeling Risk-Related Knowledge in Tunneling Projects. Risk Analysis, 2014quem mais cita →
- 8J. G. CARVALHO e C. T. COSTA. Identification Method for Fuzzy Forecasting Models of Time Series. Applied Soft Computing, 2017quem mais cita →
- 9A. P. C. CHAN e D. W. M. CHAN. A Benchmark Model for Construction Duration in Public Housing Developments. The International Journal of Construction Management, 2003quem mais cita →
- 10A. P. C. CHAN e D. W. M. CHAN. Developing a Benchmark Model for Project Construction Time Performance in Hong Kong. Building and Environment, 2004quem mais cita →
- 11D. W. M. CHAN e M. M. KUMARASWAMY. An Evaluation of Construction Time Performance in the Building Industry. Building and Environment, 1996quem mais cita →
- 12S. CHANAS e P. ZIELIÃ. Critical Path Analysis in the Network With Fuzzy Activity times. Fuzzy Sets and Systems, 2001quem mais cita →
- 13S. CHEN. Analysis of Critical Paths in a Project Network with Fuzzy Activity Times. European Journal of Operational Research, 2007quem mais cita →
- 14S. CHEN e Y.-J. HSUEH. A Simple Approach to Fuzzy Critical Path Analysis in Project Networks. Applied Mathematical Modelling, 2008quem mais cita →
- 15M. Y. CHENG. A Novel Time-Depended Evolutionary Fuzzy SVM Inference Model For Estimating Construction Project at Completion. Engineering Applications of Artificial Intelligence, 2012quem mais cita →
- 16M. H. CHUN e K. Il. AHN. Assessment of the Potential Applicability of Fuzzy Set Theory to Accident Progression Event Trees With Phenomenological Uncertainties. Reliability Engineering and System Safety, 1992quem mais cita →
- 17L. S. D. A. L. COUTINHO. Modelagem do Tempo de Execução de Obras Civis: estudo de caso na Universidade Federal do Pará. Ambiente Construído, 2012no acervo →
- 18H. M. CRUZ, D. de G. SANTOS e L. A. MENDES. Causas da Variabilidade do Tempo de Execução dos Processos em Diferentes Sistemas Construtivos. Ambiente Construído, 2018no acervo →
- 19A. CZARNIGOWSKA e A. SOBOTKA. Time-Cost Relationship for Predicting Construction Duration. Archives of Civil and Mechanical Engineering, 2013quem mais cita →
- 20L. P. FÁVERO. Análise de Dados: modelagem multivariadas para tomada de decisões. 2009quem mais cita →
Quem cita esta obra
1 artigo do acervo
quem fala desta obra
4 pessoas- Felipe Campos Alvarenga1 artigo · 2021
- Alcebíades Negrão Macedo1 artigo · 2021
- Luiz Maurício Furtado Mauésautocitação1 artigo · 2021
- Paulo Cerqueira dos Santos Júnior1 artigo · 2021
É sua obra?
Receba um aviso quando um artigo novo citar este trabalho.
também serve para acompanhar o autor que você estuda