Journal of the Brazilian Society of Mechanical Sciences and Engineering2011

Heuristic for flow shop sequencing with separated and sequence independent setup times

João Vitor Moccellin e Marcelo Seido Nagano

em inglês

cita 16 obras, 1 no acervo

resumo

This paper deals with the permutation flow shop scheduling problem with separated and sequence-independent machine setup times. A heuristic method with the objective of minimizing the total time to complete the schedule is introduced. The proposed heuristic is based on a structural property of this scheduling problem, which provides an upper bound on the idle time of the machines between the completion of the setup task and the beginning of job processing. Experimental results show that the new heuristic outperforms two existing ones.

como citar · ABNT NBR 6023

MOCCELLIN, João Vitor; NAGANO, Marcelo Seido. Heuristic for flow shop sequencing with separated and sequence independent setup times. Journal of the Brazilian Society of Mechanical Sciences and Engineering, 2011. Disponível em: https://www.scielo.br/scielo.php?script=sci_arttext&pid=S1678-58782011000100011. Acesso em: 29 nov. 2026.

Referências

16 obras citadas · 1 no acervo

  1. 1A. Allahverdi e T. Aldowaisan. "Job lateness in flowshops with setup and removal times separated". Journal of the Operational Research Society, 1998quem mais cita →
  2. 2P.C. Bagga e K. Khurana. Two-machine flowshop with separated sequence-independent setup times: mean completion time criterion. Indian Journal of Management and Systems, 1986quem mais cita →
  3. 3J. Cao e D.C. Bedworth. "Flow shop scheduling in serial multi-product processes with transfer and setup times". International Journal of Production Research, 1992quem mais cita →
  4. 4H. Campbell, R. Dudek e M. Smith. "A heuristic algorithm for the n-job m-machine sequencing problem". Management Science, 1970quem mais cita →
  5. 5T.C.E. Cheng, J.N.D. Gupta e G. Wang. "A review of flowshop scheduling research with setup times". Production and Operations Management, 2000quem mais cita →
  6. 6S.R. Das, J.N.D. Gupta e B.M. Khumawala. "A savings index heuristic algorithm for flowshop scheduling with sequence dependent set-up times". Journal of the Operational Research Society, 1995quem mais cita →
  7. 7J.N.D. Gupta e E.F. Stafford Jr.. "Flowshop scheduling research after five decades". European Journal of Operational Research, 2006quem mais cita →
  8. 8J.N.D. Gupta, V.A. Strusevich e C. Zwaneveld. "Two-stage no-wait scheduling models with setup and removal times". Computers and Operations Research, 1997quem mais cita →
  9. 9S.R. Hejazi e S. Saghafian. Flowshop-scheduling problems with makespan criterion: a review. International Journal of Production Research, 2005quem mais cita →
  10. 10S. Johnson. "Optimal two- and three-stage production schedules with setup times included". Naval Research Logistics Quarterly, 1954quem mais cita →
  11. 11K. Khurana e P.C. Bagga. "Scheduling of job-block with deadline in n X 2 flowshop problem with separated setup times". Indian Journal of Pure Applied Mathematics, 1985quem mais cita →
  12. 12J.V. Moccellin e M.S. Nagano. "Uma propriedade estrutural do problema de programação da produção flow shop permutacional com tempos de setup". Pesquisa Operacional, 2007no acervo →
  13. 13T. Park e H.J. Steudel. "Analysis of heuristics for job sequencing in manufacturing flow line work-cells". Computers and Industrial Engineering, 1991quem mais cita →
  14. 14C. Rajendran e H. Ziegler. "Heuristics for scheduling in a flowshop with setup, processing and removal times separated". Production Planning and Control, 1997quem mais cita →
  15. 15J.V. Simons Jr.. "Heuristics in flow shop scheduling with sequence dependent setup times". Omega, 1992quem mais cita →
  16. 16T. Yoshida e K. Hitomi. "Optimal two-stage production scheduling with setup times separated". AIEE Transactions, 1979quem mais cita →

Quem cita esta obra

nenhum artigo do acervo cita esta obra — ainda