An optimisation approach for capacity planning: modelling insights and empirical findings from a tactical perspective

Andréa Nunes Carvalho, Luiz Felipe Scavarda e Fabricio Oliveira

em inglês

cita 55 obras

resumo

Abstract The academic literature presents a research-practice gap on the application of decision support tools to address tactical planning problems in real-world organisations. This paper addresses this gap and extends a previous action research relative to an optimisation model applied for tactical capacity planning in an engineer-to-order industrial setting. The issues discussed herein raise new insights to better understand the practical results that can be achieved through the proposed model. The topics presented include the modelling of objectives, the representation of the production process and the costing approach, as well as findings regarding managerial decisions and the scope of action considered. These insights may inspire ideas to academics and practitioners when developing tools for capacity planning problems in similar contexts.

como citar · ABNT NBR 6023

CARVALHO, Andréa Nunes; SCAVARDA, Luiz Felipe; OLIVEIRA, Fabricio. An optimisation approach for capacity planning: modelling insights and empirical findings from a tactical perspective. Production, 2017. DOI: 10.1590/0103-6513.001417.

Referências

55 obras citadas

  1. 1D. Alem e R. Morabito. Production planning in furniture settings via robust optimization. Computers & Operations Research, 2012quem mais cita →
  2. 2A. Alfieri, T. Tolio e M. Urgo. A project scheduling approach to production planning with feeding precedence relations. International Journal of Production Research, 2011quem mais cita →
  3. 3A. Alfieri, T. Tolio e M. Urgo. A two-stage stochastic programming project scheduling approach to production planning. International Journal of Advanced Manufacturing Technology, 2012quem mais cita →
  4. 4C. Artigues, R. Leus e F. Nobibon. Robust optimization for resource-constrained project scheduling with uncertain activity durations. Flexible Services and Manufacturing Journal, 2013quem mais cita →
  5. 5B. Aslan, M. Stevenson e L. Hendry. Enterprise Resource Planning systems: an assessment of applicability to Make-To-Order companies. Computers in Industry, 2012quem mais cita →
  6. 6M. Bushuev. Convex optimization for aggregate production planning. International Journal of Production Research, 2014quem mais cita →
  7. 7G. Buxey. Strategy not tactics drives aggregate planning. International Journal of Production Economics, 2003quem mais cita →
  8. 8G. Buxey. Aggregate planning for seasonal demand: reconciling theory with practice. International Journal of Operations & Production Management, 2005quem mais cita →
  9. 9N. S. Cameron e P. M. Braiden. Using business process re-engineering for the development of production efficiency in companies making engineered to order products. International Journal of Production Economics, 2004quem mais cita →
  10. 10A. N. Carvalho, F. Oliveira e L. F. Scavarda. Tactical capacity planning in a real-world ETO industry case: an action research. International Journal of Production Economics, 2015quem mais cita →
  11. 11A. N. Carvalho, F. Oliveira e L. F. Scavarda. Tactical capacity planning in a real-world ETO industry case: a robust optimization approach. International Journal of Production Economics, 2016quem mais cita →
  12. 12A. N. Carvalho, L. F. Scavarda e L. J. Lustosa. Implementing finite capacity production scheduling: lessons from a practical case. International Journal of Production Research, 2014quem mais cita →
  13. 13H. Chtourou e M. Haouari. A two-stage-priority-rule-based algorithm for robust resource-constrained project scheduling. Computers & Industrial Engineering, 2008quem mais cita →
  14. 14D. Corti, A. Pozzetti e M. Zorzini. A capacity-driven approach to establish reliable due dates in a MTO environment. International Journal of Production Economics, 2006quem mais cita →
  15. 15P. Coughlan e D. Coghlan. Action research for operations management. International Journal of Operations & Production Management, 2002quem mais cita →
  16. 16F. Deblaere, E. Demeulemeester e W. Herroelen. Proactive policies for the stochastic resource-constrained project scheduling problem. European Journal of Operational Research, 2011quem mais cita →
  17. 17M. Díaz-Madroñero, J. Mula e D. Peidro. A review of discrete-time optimization models for tactical production planning. International Journal of Production Research, 2014quem mais cita →
  18. 18M. J. R. Ebben, E. W. Hans e F. M. O. Weghuis. Workload based order acceptance in job shop environments. OR-Spektrum, 2005quem mais cita →
  19. 19B. Fernandes, A. Street, D. Valladão e mais 1. An adaptive robust portfolio optimization model with loss constraints based on data-driven polyhedral uncertainty sets. European Journal of Operational Research, 2016quem mais cita →
  20. 20N. Gademann e M. Schutten. Linear-programming-based heuristics for project capacity planning. IIE Transactions, 2005quem mais cita →
1–20 de 55 obras citadas

Quem cita esta obra

nenhum artigo do acervo cita esta obra — ainda

É sua obra?

Receba um aviso quando um artigo novo citar este trabalho.

também serve para acompanhar o autor que você estuda
Acompanhar as citações