Anais da Academia Brasileira de Ciências2026
Optimization of Bench Geometry for Efficient Slope Stability and Overburden Removal in Open Pit Mining
TUĞÇE ÖNGEN, ÇAĞRI ÇERİK e MUSTAFA EMRE YETKİN
em inglês
resumo
Abstract Open-pit mining operations require a careful balance between maintaining slope stability and minimizing the amount of overburden to be removed. In this study, different bench geometries were examined to determine the most efficient configuration that satisfies both safety and economic considerations. Thirteen pit models were created and analyzed through finite element simulations, and the results were further evaluated using the Response Surface Methodology (RSM) based on a three-factor, three-level Box–Behnken experimental design. The analysis focused on three key parameters: bench height (H), berm width (W), and bench slope angle (β). Optimization was carried out to achieve a factor of safety (FoS) of at least 1.2 while minimizing overburden removal. The optimal design was obtained for H = 8 m, W = 8 m, and β = 75°, yielding a FoS of 1.23 and a stripping ratio of about 20.6 m³/ton. Verification through finite element modeling confirmed the reliability of the proposed model with 98.3% accuracy. The findings emphasize that integrating numerical modeling with experimental optimization techniques can effectively guide safe and economically viable open-pit designs.
como citar · ABNT NBR 6023
ÖNGEN, TUĞÇE; ÇERİK, ÇAĞRI; YETKİN, MUSTAFA EMRE. Optimization of Bench Geometry for Efficient Slope Stability and Overburden Removal in Open Pit Mining. Anais da Academia Brasileira de Ciências, 2026. DOI: 10.1590/0001-3765202620251145.
Referências
47 obras citadas
- 1A AGOSTI, UTILI STEFANO, C VALDERRAMA e mais 1. Optimal pitwall profiles to maximise the overall slope angle of open pit mines: the McLaughlin Mine. Aust Cent Geomech, 2021quem mais cita →
- 2LR ALEJANO, B PONS, FG BASTANTE e mais 2. Slope geometry design as a means for controlling rockfalls in quarries. Int J Rock Mech Min Sci, 2007quem mais cita →
- 3FK ALTUNTOV e M ERKAYAOĞLU. A New Approach to Optimize Ultimate Geometry of Open Pit Mines with Variable Overall Slope Angles. Nat Resour Res, 2021quem mais cita →
- 4X BAI, G TURCZYNSKI, N BAXTER e mais 3. Pseudoflow Method for Pit Optimization. 2017quem mais cita →
- 5RP BORGES, L BACELLAR, CB GRASSO e mais 2. Slope geometry optimization considering groundwater drawdown scenarios at an open-pit phosphate mine, southeastern Brazil. Environ Earth Sci, 2023quem mais cita →
- 6GEP BOX e DW BEHNKEN. Some New Three Level Designs for the Study of Quantitative Variables. Technometrics, 1960quem mais cita →
- 7CIM. CIM Estimation of Mineral Resources & Mineral Reserves Best Practice Guidelines Prepared by the CIM Mineral Resource & Mineral Reserve Committee Canadian Institute of Mining, Metallurgy and Petroleum. 2019quem mais cita →
- 8DASSAULT SYSTEMES. GEOVIA Surpac | Geology & Mine Planning - Dassault Systèmes®. 2021quem mais cita →
- 9N DESTANOGLU, FB TASKIN, M TASTEPE e mais 1. Omerler mechanized longwall application. Turkish Coal Administration, 2000quem mais cita →
- 10E ELAHI, R KAKAIE e A YUSEFI. A new algorithm for optimum open pit design: Floating cone method III. J Min Environ, 2012quem mais cita →
- 11F FERRARI, K THOENI, A GIACOMINI e mais 1. A rapid approach to estimate the rockfall energies and distances at the base of rock cliffs. Georisk Assess Manag Risk Eng Syst Geohazards, 2016quem mais cita →
- 12A GIACOMINI, K THOENI, C LAMBERT e mais 2. Experimental study on rockfall drapery systems for open pit highwalls. Int J Rock Mech Min Sci, 2012quem mais cita →
- 13W GIBSON, IA DE BRUYN e DJH WALKER. Considerations in the optimisation of bench face angle and berm width geometries for open pit mines. The South African Institute of Mining and Metallurgy, 2006quem mais cita →
- 14W GUO, G LIU, J LI e mais 2. Research on the method of determining the block size for an open-pit mine integrating mining parameters and shovel-truck’s operation efficiency. Sci Rep, 2024quem mais cita →
- 15HL HARTMAN e JM MUTMANSKY. Introductory mining engineering. 2002quem mais cita →
- 16WA HUSTRULID, M KUCHTA e RK MARTIN. Open pit mine planning and design. 2013quem mais cita →
- 17TB JOHNSON e WR SHARP. A Three-dimensional Dynamic Programming Method for Optimal Ultimate Open Pit Design. 1971quem mais cita →
- 18E KOENIGSBERG. The optimum contours of an open pit mine: an application of dynamic programming. Society for Mining, Metallurgy & Exploration, 1982quem mais cita →
- 19H KOSE, C TATAR, G KONAK e mais 2. T.K.İ. Garp Linyitleri İşletmesi Müessese Müdürlüğü Ömerler Yeraltı İşletmesi Tabaka Kontrolü, Yük ve Konverjans Ölçümleri (Proje Raporu). 1994quem mais cita →
- 20H LERCHS. Optimum Design of Open-Pit Mines. CIM Bull, 1965quem mais cita →
Quem cita esta obra
nenhum artigo do acervo cita esta obra — ainda
É sua obra?
Receba um aviso quando um artigo novo citar este trabalho.
também serve para acompanhar o autor que você estuda